Construction of taxiway parallel to the runway in the Gdansk Lech Walesa Airport
Developing the project
The taxiway has been designed as the asphalt pavement of the strip 23 m wide with reinforced shoulders on both sides,each 7.5 m wide. Taxiway length amounts to 2,6 km, whereas its surface with exit ways and reinforced shoulders is 126,500 m².
The project in figures
- excavations ~ 125 000 m3
- embankments ~ 95 000 m3
- surface ~ 178 000 m2
- built-in material:
- crushed-stone aggregate ~ 70 000 t
- mineral and asphalt mixes: ~ 110 000 t